During our meeting discussion about the rework process the below items have been finalizedOverview

Yakta has a reworked process where Mowers and Finish goods are returned and modified as per the new design, based on the dealer requirements and complaints, below are proposed general steps for rework process.

  1. Create a new work order , with Same for the return finish good items with different Serial number and consume the FG and add the raw material to do process the new rework work order -

  2. Yakta has decided to use the New Serial number will be assigned. Old Serial number will not be utilized.

    1. Goldfinch need to test the rework Work order is in the system but we need to test it.

    2. Quantity will be allocated but not the Serial number.

    Output bin to Shipment Bin

    1. we need 1 week as discussed to complete this task.